This story was published Fri, Jun 21, 2002 HERMISTON -- Recent problems at the Umatilla Chemical Depot have created
further delays in the destruction of the nerve agent stockpile. Army officials said Thursday that agent burns won't begin until "at
least" May 2003. Don Barclay, project manager for the Army's Chemical Demilitarization
Program, alerted the Citizens Advisory Committee of the delay -- the latest
in a series of delays -- during a meeting Thursday at Good Shepherd Hospital
in Hermiston. The Army previously had set February as the target date to begin burning
the 3,717 tons of VX, sarin and mustard gas stored at the site. Barclay said the delay is because of technical problems with the continuous
emissions monitoring systems attached to the depot's incinerators. Those problems bumped the test burns deadline, originally scheduled May
25, by a couple of months. Barclay said July 24 is the new target date to
begin test burns. Bob Flournoy, committee chairman, said the Army is making the right decision. "This delay is for safety factors. We're not going to do anything
until we know as best we can, it's safe. Even if we have to delay the project
to accomplish that," Flournoy said. Barclay insisted the delay is not hurting the bottom line for Washington
Demilitarization Co., the contractor hired to destroy the chemicals, or
the Army. "It has not had a financial impact," Barclay said. Barclay said there are incentives built into Washington Demilitarization
Co.'s contract based on the schedule. Instead, Barclay said the Army built into the contract a safety component
that balances out any schedule delays. "As a customer, what the Army wants from them is safety first,"
he said. Some board members, who didn't want to be identified, expressed
skepticism about the Army's contention the delay doesn't have a financial
impact. Estimates were placed between $200,000 to $400,000 a day in cost
overruns. Wayne Thomas, project manager for the Oregon Department of Environmental
Quality, said the Army repeatedly has told environmental regulators that
it costs $325,000 a day to operate the facility. Copyright 2002 Tri-City Herald. All rights reserved. This material
may not be published, broadcast, rewritten or redistributed.

Depot burning delayed once more