This story was published Wed, Oct 3, 2001 Pentagon officials said Tuesday that it was unlikely the United States
will make the 2007 treaty deadline for destroying the weapons, and $9 billion
more than originally expected will be required to do it. In a meeting with three Alabama lawmakers, E.C. "Pete" Aldridge
Jr., undersecretary of defense for acquisition, technology and logistics,
said he altered the completion schedule for at least four of eight incineration
sites to answer safety concerns from surrounding residents. Aldridge also said the cost of incineration is now estimated at $24 billion,
up from the $15 billion originally projected. "We've adjusted both the schedule and program cost to what I think
is the highest confidence I can provide," Aldridge said. Under the new schedule, incineration of the weapons at the Umatilla Chemical
Depot, originally scheduled to be completed in mid-2005, is now expected
to continue until at least December 2008 in a best-case scenario. Any delays
could push that timeline to mid-2013. Originally, test burns were scheduled to begin this month, with incineration
to start in July 2002. In January, Wayne Thomas, an Oregon Department of
Environmental Quality official in charge of chemical demilitarization, said
testing would be delayed at least six weeks. The Army followed with an announcement
in August that incineration would not start until February 2003. Karyn Jones, a member of the Chemical Weapons Working Group, a grass-roots
organization based in Berea, Ky., that opposes chemical incineration, said
the delays are no surprise. "I think I followed progress at (Johnston Island) closely over the
past 11 years, and I know they were continually behind schedule," said
Jones, who lives in Hermiston. Last spring, an internal Army memo revealed doubts on whether the deadline
could be met and concluded it could require up to 11 extra years to destroy
all the weapons. At the time, Pentagon officials dismissed that as a worst-case
scenario. That deception is what most bothers Craig Williams, also a member of
the Chemical Weapons Working Group. "The communities deserve accurate and honest information so they
understand what is going on," Williams said. "This program has
a long history of misrepresentation, not only to its cities, but also to
Congress." Don Barclay, site project manager at the Umatilla incineration plant,
said he is not concentrating on the completion date right now. "We must focus on our operational start date, because we can't reduce
the risk until we start," Barclay said. Incineration at all the sites will take longer than anticipated and the
sites in Umatilla, Pine Bluff, Ark., and Newport, Ind., will miss the treaty
deadline. A completion date hasn't been determined for Blue Grass, Ky.,
and Pueblo, Colo. Only Aberdeen, Md., and Tooele, Utah, which has already
begun burning, remain on track to beat the treaty deadline. The Army has stockpiled nearly 30,000 tons of the deadly chemicals, which
have been scheduled to be destroyed by 2007 as part of an international
chemical weapons treaty. Internal Army documents have raised doubts on whether
that deadline could be met. But this is the first time Pentagon officials
have acknowledged a delay. Copyright 2002 Tri-City Herald. All rights reserved. This material
may not be published, broadcast, rewritten or redistributed.

Depot faces longer deadline