This story was published Thu, May 24, 2001 HERMISTON - Nearly four years and 24,000 cubic yards of concrete later,
construction of the Umatilla Chemical Depot incinerator plant is complete. But many more nuts and bolts must be tightened before any chemical weapons
can be destroyed there. It could take up to 18 months to complete the testing
required before any burning can start. The $567 million plant was completed 13 days ahead of the May 29 contract
deadline, said Loren Sharp, Washington Demilitarization Co.'s program manager,
who called the early completion a "major victory." Washington Demilitarization took over the contract from Raytheon Demilitarization
Co. last summer. The plant is composed of four incinerators that will be used to destroy
the 7.4 million pounds of deadly nerve and mustard agents stored at the
Umatilla Chemical Depot, seven miles west of Hermiston. Much of the agents
are in weapons such as rockets, some of which have leaked. Now the builders face the daunting task of testing all the incinerator's
components - each valve, gauge, motor and socket - to make sure everything
is in working order. "This is when we find out if everything is up to par and fix the
things that aren't," said Rick Kelley, Washington Demilitarization
spokesman. The process starts with the testing of the smaller parts, down to light
bulbs and sockets, and ends with trial burning. The plant's parking lot is sparse now compared with what it looked like
in July 1999 when 1,146 workers were on the site. Those workers moved more than 300,000 cubic yards of earth, used 2,655
tons of steel to reinforce concrete and strung 971 miles of electrical wire
and conduit. Only 63 employees remain to test the equipment, Kelley said. Depot Commander Lt. Col. Tom Woloszyn said completion of the plant is
significant, but right now he is focusing on getting his people trained
and ready to handle the chemical weapons. Woloszyn said he is receiving surrogate rounds, which will be used to
test the incinerators. Those are being stored in igloos similar to those
where the chemical weapons are stored in the depot's K Block area. Then workers will be trained to move the weapons using forklifts and
special vehicles. "We have to crawl, walk and then run with the ammunition handlers,
even if they have been here for years," Woloszyn said. "They must
continue training." The reason for all the time, testing and training is right under the
nose of Eastern Oregon residents, as the Army reported its third leaking
weapon within a week. Army spokesman Jim Hackett said a depot crew detected a trace amount
of sarin gas Wednesday morning in the same igloo where two weapons leaked
last week. The weapons stored in the igloo have leaked before and have been "overpacked"
in other containers, Hackett said. "These weapons have been out here for 39 years," he said. "They
are bound to deteriorate at some point, not to say this rash of leakers
is an indication of that. But the Army has recognized all along that long-term
storage is riskier than incineration." The Army has reported 134 total leakers since 1984. Eight weapons have
leaked more than once, Hackett said. Although the original plans called for five incinerators, only four were
built - one metal parts furnace, two liquid furnaces and a deactivation
furnace. The dunnage incinerator, which was going to be used to consume secondary
waste, has been put on hold. Wayne Thomas of the state Department of Environmental Quality said the
Army wants to see if there is a more efficient way to get rid of the secondary
waste - the protective suits, gloves and other items that will be contaminated
as employees destroy the chemical weapons. Thomas said the Army has successfully used the metal parts furnace at
its Johnston Island plant to destroy the protective suits and is still studying
different ways of dealing with the waste. Copyright 2002 Tri-City Herald. All rights reserved. This material
may not be published, broadcast, rewritten or redistributed.

Incinerator done; testing next step