This story was published Sat, Jan 20, 2001 HERMISTON - Although construction of the Umatilla Chemical Depot's incinerator
is nearly complete, the Oregon Department of Environmental Quality says
testing of the facility likely will be delayed at least six months and incineration
isn't likely to start before 2003. Wayne Thomas, DEQ program administrator, said under the current Army
schedule, construction should be complete by May, and testing of the incinerators
should start in October, with operations following in July 2002. "They have too much to do," Thomas said. "There is a wide
range of issues with the U.S. Army and the contractor related to the permit
that must be resolved before testing can start." That includes decisions on how secondary waste will be managed and trial
burn plans that need to be reviewed. Thomas said the trial burn plans must
be received at least 180 days before testing can begin. In addition, the Chemical Stockpile Emergency Preparedness Program must
prove it's ready to protect local communities if a chemical event occurs.
Gov. John Kitzhaber is requiring a full report from the Executive Review
Panel regarding CSEPP, and the governor said he will not allow testing until
he is sure CSEPP can do its job. "We are disappointed (by the DEQ's report) that there will be a
slight delay, but it gives the community a chance to increase preparedness
even more than they already had," said Chris Dearth, environmental
projects director for the governor's office. But the Army doesn't necessarily agree with the DEQ prediction, said
Gary Anderson, the Army's interim site project manager. "The delays are DEQ's assessment," Anderson said. "We
are still on target and working toward the July 2002 chemical operations
date. We have a lot of significant work to accomplish to maintain that date,
but it is the date we are holding to right now." Schedule changes are nothing new for the $1.2 billion project that is
to destroy 3,717 tons of chemical weapons stored at the depot seven miles
west of Hermiston. The Army's original incineration date was October 2001,
which was later changed to mid-2002. Copyright 2002 Tri-City Herald. All rights reserved. This material
may not be published, broadcast, rewritten or redistributed.

DEQ says testing of depot incinerator likely will be delayed