This story was published Wed, Mar 31, 1999 HERMISTON - Construction of the incinerator at the Umatilla Chemical
Depot is about 10 months behind schedule, but the delay apparently won't
postpone the target date to begin burning the weapons stockpile stored there. Officials first estimated the state's largest construction project would
be finished by April 2000, but that date has been pushed back to February
2001. The partners building the incinerator said Tuesday that the date to begin
destroying the weapons remains October 2001 and plans to have the weapons
stockpile completely destroyed still are scheduled for 2005. What remains a question mark is how much more it will cost to build the
incinerator. Last fall, the Army - one of the partners in the project - tentatively
approved an additional $5.7 million to cover the costs of certain design
and structural changes to the project. That would have elevated the price
tag from $567 million to about $572 million. But the Army Corps of Engineers, which is overseeing the construction
project, said the earlier $5.7 million estimate would go up. "It will be more than that," Bob DeMichele, the corps' public
affairs officer in Huntsville, Ala., said Tuesday. "There'll be a cost
associated with this, but we have to see how big a cost it turns out to
be." The most up-to-date figure for the project's cost is to be part of a
detailed plan the Army is expecting to receive at the end of May from Raytheon
Demilitarization Co., the contractor building the incinerator, DeMichele
said. "We have a 60-day agreement with Raytheon that they will give us
something detailed on how to adjust the schedule," DeMichele said.
"We can meet the toxic operations deadline. No one has any concern
we couldn't do that. Now, it's agreeing on how that process will go." The incinerator is under construction at the depot site eight miles west
of Hermiston to destroy the 3,717 tons of aging lethal nerve agents stored
there. Under an international Chemical Weapons Convention treaty, the Army
must have its stockpile destroyed by April 2007. The Army has estimated in a worst-case scenario that continued storage
of the deteri orating chemical stockpile could result in the death of more
than 10,000 people within a 62-mile radius of the depot. Raytheon officials said Tuesday that modifying the construction schedule
allows them to remain on track to burn the weapons by testing certain parts
of the plant before construction of the plant is completed. Originally, testing of the incinerator, otherwise known as systemization,
wasn't going to begin until October 2001. Under Raytheon's contract modification,
the company won't wait to find out if the facility is working right and
can begin testing during the construction phase. "A lot of the systemization activities we perform don't need a complete
plant, down to the light bulbs and light sockets," said Chris Early,
Raytheon's protocol officer. "We have a way to build the plant safely and operate efficiently
and meet our toxic operation date. We're all happy that we found a way to
get there and we're going there." But Early recognizes Raytheon's current contract modification and other
design changes to the incinerator project mean more money. "The $567 million is the original contract number and the changes
in design, including this modification, are going to affect that number,"
Early said. Those changes to the plant run the gamut, from moving a wall to adding
vestibules or an anteroom to the plant's special air purifying, carbon filter
system. Mary Binder, the Army's public affairs officer, compares the design and
structural changes to those any resident might face who is building a house. "As you get into the actual construction and what you see on paper,
in most cases, there will be some modification that you make along the way
that affects the time line," Binder said Tuesday. When asked if the construction completion date could change again in
the future, Binder said the possibility exists. "The goal for everybody
is meeting the treaty requirements and the program requirements," Binder
said. "Those goals and those time frames have not changed." Copyright 2002 Tri-City Herald. All rights reserved. This material
may not be published, broadcast, rewritten or redistributed.

Weapons burning expected to start on schedule